Repowering Karpathos
- Planning, financing and implementation of the first repowering windturbine in Greece by replacement of a Nordex N-43 by an Enercon E-44-turbine (w/ Wootis u. Zephiros). Due to grid constraints on the island of Karpathos the capacity could not be increased.
PV Greece, 2020
- Project development, financing, implementation, owning and operation of several PV stations with a total capacity of 7MWp in Evros, Greece (w/ Wootis and Zephiros).
Windfarm Schale, 2020
- Project development, permitting, financing, implementation and operation of two wind turbines each with 4,5 MW in Hopsten / district of Steinfurt (w/ PEG / EEG).
Windfarm Schwege, 2019
- Project development, permitting, financing, implementation and operation of four wind turbines each with 3,6 MW in Glandorf / district of Osnabrück (w/ PEG / EEG).
Windfarm Settrup, 2018
- Project development, permitting, financing, implementation and operation of three wind turbines each with 4,2 MW in Fürstenau / district of Osnabrück (w/ PEG).
Windfarm Sellberg-Utdrift, 2017
- Project development, permitting, financing, implementation and operation of five wind turbines each with 4,2 MW in Fürstenau the district of Osnabrück (w/ PEG).
Windturbine Tammhausen, 2017
- Repowering of an existing 1,3MW-turbine against a 3,3MW-turbine in Wilhelmshaven. Project development, permitting, financing, implementation and operation.
Windfarm Haneberg-Ohrte, 2016
- Permitting for three Senvion 3.2M122 in the district of Osnabrück (w/ PEG).
Windfarm Badbergen / Germany, 2016
- Project development, permitting, financing, implementation and operation of 2 wind turbines each with 2,4 MW in the district of Osnabrück (w/ PEG / EEG).
Windfarm Gehrde / Germany, 2015
- Project development, permitting, financing, implementation and operation of 4 wind turbines each with 3 MW in the district of Osnabrück (w/ PEG / EEG).
Thunder Spirit / USA, 2015
- Project development for 43 wind turbines of 2.5 MW in North Dakota (w/ Windworks Power and Global Winds Harvest).
Windfarm Brockhausen / Germany, 2014
- Project development, permitting, financing and implementation of 3 wind turbines each with 3 MW in the district of Osnabrück (Order development for landowners, w/ EEG).
Windfarm Ippenburg / Germany, 2014
- Project development, permitting, financing, implementation, owning and operation of 2 wind turbines each with 2,4 MW in the district of Osnabrück (w/ EEG).
Windturbine Ellerbeck / Germany, 2014
- Project development, permitting, financing and implementation a 2,5MW wind turbine in the district of Osnabrück (w/ PEG / EEG).
PV Salzwedel / Germany, 2012
- Project development, financing, construction, owning and operating of a 2MWp ground mounted PV system near Magdeburg (w/ BioConstruct).
Ontario / Canada, 2008 – 2012
- Project development for 100 multi megawatt wind turbines (w/ Windworks Power).
PV Fonte Cupa / Italy, 2011
- Development and construction of a 650 kWp ground mounted PV system near Perugia in Umbria (w/ BioConstruct).
PV Greece, 2006 – 2011
- Project development for ground-mounted PV systems with a total capacity of more than 100 MWp (W/ various partners).
ATZ – Agrar-Technologie-Zentrum Melle / Germany, 2011
- Project development, permitting, financing, implementation and operation of a 1MW biogas plant and a renewable resource-wood gasification plant with heat supply of properties in in Melle (w/ BioConstruct).
PV Koumaria and Pente Dromi / Greece, 2010
- Project development, financing, implementation, owning and operation of two 200 kWp PV systems on the Peloponnese
(w/ Zephiros).
Windfarm Tatanka / USA, 2008
- Project development for 120 wind turbines of 1.5 MW in North Dakota (w/ Global Winds Harvest).
Windfarm Bear Creek, P.A. / USA, 2006
- Project development for 12 wind turbines of 2.0 MW in Pennsylvania (w/ Global Winds Harvest).
Biogas plant Kaarßen / Germany, 2005
- Project development, permitting, financing, implementation, owning and operation of a 2.8 MW biogas plant near Lüneburg (w/ BioConstruct).
Windfarm Bad Essen / Germany, 2005
- Project development and implementation of four 2.0 MW wind turbines in the district of Osnabrück (w/ EEG)
- Citizen participation offered through a limited partnership managed by WKN AG.
Windparks Evia / Karpathos, Greece, 2002/3
- Project development, implementation and operation of six 600 kW wind turbines on the peninsula of Evia and on the island of Karpathos (w/ Zephiros).
Windfarm Hohnsleben / Germany, 2003
- Project development, permitting, financing, implementation and operation of two 1.5 MW wind turbines in the area of Helmstedt (w/ EEG).
- Citizen participation through limited partnership.
Windfarm Badbergen-Dinklage / Germany, 2002
- Project development, permitting, financing, implementation and operation of 17 wind turbines each with 1.5 MW in the district of Osnabrück (w/ SeeBA / EFI).
- Citizen participation offered in eight wind turbines by a limited partnership (managed by EFI Wind GmbH).
- Management of the grid connection company.
Windfarm Hochfeld / Germany, 2001
- Project development, permitting, financing, implementation and operation of three 1.3 MW wind turbines in the area of Itzehoe.
- Citizen participation through limited partnership.
Windfarm Schuby / Germany, 2001
- Project development, permitting, financing, implementation and operation of 12 wind turbines each with 1.5 MW in the region of Schleswig.
- Citizen participation through limited partnership.
- Technical and operational management services: EEGST GmbH.
Region Regenerativ MELLE (RRM) / Germany, 2001/2002
- Initial Goal: to generate 100% of electricity consumption in the city of Melle (district of Osnabrück) on a renewable basis.
- Project design and development, permitting and financing. Implementation and operation of six 1.5 MW wind turbines (w/ EEG).
- Citizen participation through limited partnerships and in additionPermitting, financing and operation of various PV and biogas plants.